Capital Projects

The Township of Elizabethtown-Kitley has invested in the following Capital Projects for 2024.
These projects are in accordance with our long term goals and Strategic Plan.

Administration
Project Name: Type of Project: Basis for Activity: Description Process To Date
Website Redesign Information Technology Service Level Change To engage the services of a 3rd party developer to assist with an overhaul of the Township website to make it more user friendly and edit friendly View Strategic Plan Relationship(s)
Digital Signature Platform Information Technology Service Level Change The purchase and implementation of a digital signatures platform View Strategic Plan Relationship(s)
Fire
Project Name: Type of Project: Basis for Activity: Description Process To Date
Replace 1995 Kitley KR03 Rescue Vehicle Fleet Asset Renewal Replacement rescue vehicle for Station No. 03 View Strategic Plan Relationship(s)
Battery Operated E Draulics (Rescue Tools) Equipment Asset Renewal

Department wide transition to battery operated hydraulics includes:

 2- SP 28-inch spreaders, 2- S E3 Cutters, 2- R E3 Rams, 1- SC E3 Combination Tool,     14 – Batteries, 7 – E3 Chargers

View Strategic Plan Relationship(s)
Replace 2000 Tanker #2 Fleet Asset Renewal To Replace tanker # 2 View Strategic Plan Relationship(s)
Rescue # 1 – Upgrades Vehicle Upgrade to asset Upgrades to Rescue to accommodate secure storage of battery-operated rescue tools View Strategic Plan Relationship(s)
Parks & Recreation
Project Name: Type of Project: Basis for Activity: Description Process To Date
Blaine Healey Pavillion/Canteen Facilities Asset Renewal Complete the Pavilion Project by transferring the electrical panels located in the old canteen building that control the Diamond lights over to the new utility room within the pavilion. View Strategic Plan Relationship(s)
Play Structure – Eleanor Fulford Equipment Asset Renewal Replacing the aged and undersized play structure in a growing family community. View Strategic Plan Relationship(s)
Bellamy Park Office Facilities Asset Renewal In August, 2023, Council, through Report No. A-23-78 authorized the tenant to renovate the existing office, primarily exterior work by replacing all windows and doors, re-siding the entire structure and enhancing the internal floor base, to a maximum cost of $20K, to be funded from the Bellamy Park Reserve. View Strategic Plan Relationship(s)
Public Works
Project Name: Type of Project: Basis for Activity: Description Process To Date
Tandem Plow Truck #10 Vehicle Asset Renewal Tandem plow truck replacement for unit # 10 ( pre approved in 2023) View Strategic Plan Relationship(s)
Truck #5 F550 – Used Vehicle Asset Renewal To replace unit # 5 with a newer asset View Strategic Plan Relationship(s)
Water Tank Replacement Equipment Asset Renewal To purchase a new water tank to fit current fleet View Strategic Plan Relationship(s)
3 Ton Asphalt Box – Used Equipment Service Level Change To purchase a used hot box for asphalt View Strategic Plan Relationship(s)
Utility Trainer Equipment Service Level Change To purchase a utility trailer View Strategic Plan Relationship(s)
Portable Packer (Roller) – Used Equipment Service Level Change To purchase a portable packer (roller) View Strategic Plan Relationship(s)
Kitley Line 3 Road Construction Asset Renewal

Reconstruction of a section of Kitley Line 3 – 1.1 kms from Hughes Road.

Work includes full depth reconstruction (pulverization of existing asphalt, fabric overlay, 6 inches B gravel, 4 inches A gravel and finished with asphalt surface.

View Strategic Plan Relationship(s)
New Dublin Road Road Construction Asset Renewal

Reconstruction of a 1.9 km section of New Dublin Road from 6th Concession Road to CR 29.

Work includes pulverization of existing roadway, 4 inches of A gravel and asphalt overlay.

View Strategic Plan Relationship(s)
Graham Lake Road Road Construction Asset Renewal

Reconstruction of 2.6 km between CR 46 and the FOY border.

Work includes pulverization of existing roadway, fabric overlay, 4 inches A gravel, 8 inches B gravel and double surface treatment with fog sealer.

View Strategic Plan Relationship(s)
Old Sharpe’s Lane (South of 401) Road Construction Asset Renewal

Reconstruction of a 100m road plus 30m cul-de-sac.

Work includes excavation of existing deteriorated roadway,

fabric overlay, 4 inches A gravel, 8 inches B gravel for road and 12 inches B gravel for cul-de-sac and 50mm asphalt.

View Strategic Plan Relationship(s)
Applewood Circle Road Construction Asset Renewal

Reconstruction of cul-de-sac from 2nd Concession Road to dead end.

Work includes excavation of existing deteriorated roadway to enhance drainage and ditching, fabric overlay, 4 inches B gravel and 50mm asphalt.

View Strategic Plan Relationship(s)
Long Beach Drive Road Construction Asset Renewal

Reconstruction of 350m of this dead-end cul-de-sac.

Work includes pulverization of existing roadway, 4 inches A gravel, 12 inches B gravel and 50mm asphalt.

View Strategic Plan Relationship(s)
Butternut Bay Road Road Construction Asset Renewal

Reconstruction and paving of .2km from Brockmere Cliff

Work includes excavation of existing deteriorated roadway, ditching, drainage improvements, stabilization of base for 50mm asphalt.

View Strategic Plan Relationship(s)
Crystal Road Roads Construction Asset Renewal

Reconstruction of 1500m of Crystal Road.

Work includes pulverization, fabric overlay, 4 inches A gravel, 8 inches B gravel and finished with tar and chip.

View Strategic Plan Relationship(s)
Crack Sealing Preventative Maintenance Asset Life Cycle Maintenance Participation in the UCLG Crack Sealing RFP to initiate a pavement preservation capital program for the Township road network. View Strategic Plan Relationship(s)